In progress, October to November 2026. Perfect Contracting is carrying out the concrete demolition of the old coach ramp at Roma Street Station in Brisbane for the CBGU Design and Construct Joint Venture, as part of the Cross River Rail program. The ramp is a suspended reinforced concrete deck on concrete columns, sitting between retained basement walls that have to stay standing and undamaged when we leave.
This is a big one for our Queensland team. It is the first time Perfect Contracting has run a 35 tonne excavator on a Brisbane job, and we sent it up by road from New South Wales to do it. Paired with a 14 tonne machine and a track mounted wall saw, it has let the crew take the deck down in controlled sections without loading the structure that stays behind.

The job
The coach ramp is one of the last pieces of the old Roma Street layout. It has to come out so the new station works can carry on around it. The joint venture asked us to remove the deck and its columns, protect the retained walls and their ground anchors, and leave a clean edge for the next trades.
We have worked at Roma Street for the same joint venture since April 2025. The earlier packages, from platform slab demolition to wire sawing and wall penetrations, are on our Roma Street Station project page. The coach ramp is a straight piece of heavy concrete demolition in Brisbane, and a different kind of job to the work inside the station.


What the job involved
- Anti-throw fencing and screens installed along the ramp edges on night shift before any demolition started
- Excavators floated in overnight so the street and the busway were clear by morning
- Timber protection built over the ground anchors on the retained walls
- Saw cutting along the ramp walls with a track mounted wall saw to free the deck from the structure that stays (concrete cutting in Brisbane)
- Deck demolition in strips with the 35 tonne and 14 tonne excavators, using hammers, a pulveriser and grabs
- Column removal once each strip of deck was clear
- Water suppression on every break for silica dust, with fit tested respirators for the crew
- Concrete and reinforcing steel kept apart on site for load out
A 35 tonne excavator on a Brisbane job, a first for us
Most of our earlier work at Roma Street was inside the station, done with compact plant and remote controlled demolition machines. The coach ramp needed reach and weight. A suspended deck this size is quicker and safer to take down with a big machine standing well back from the edge than with small gear working underneath it.
So we moved our 35 tonne excavator up from a job in Bathurst. It travelled up over two days with its attachments following on a second truck, and it was floated onto site on night shift with the 14 tonne machine. For a Queensland crew that has built its name on tight, careful work in the city, putting a machine of that size to work in the middle of Brisbane is a real step up. It means we can now bring our own heavy plant to large demolition jobs in Queensland.




What made it hard
The ramp sits inside a working station precinct, with the busway, the station and other contractors all within a short distance of the demolition zone. Nothing could leave the exclusion zone, so the edges were fenced and screened, and the work was held inside barriers every shift.
The walls either side of the ramp are staying. They carry ground anchors that hold the basement in place, so every anchor head was boxed in timber and the deck had to be cut free before it was broken. Vehicles are not allowed inside the work area, so the crew set up to service the plant from the gate and planned each day around that.
The deck itself is heavily reinforced. The saw cutting had to go slowly through the steel, and the crew learned quickly how to set the feed so the blade kept moving without binding.


How it was done
Cut first, break second. That is how we run every job at Roma Street. The cut lines along the ramp walls were marked out and sawn with the wall saw, with cuts about 300 mm deep. Once the deck was separated from the walls that stay, nothing we did to it could pull on the retained structure.
Our site supervisor changed the sequence from the original plan so the deck comes off in strips about 2 metres wide, working from west to east, with the last section left until the end. The 35 tonne excavator works from the ground well back from the edge, breaking and pulling each strip, while the 14 tonne machine clears the rubble and cleans up against the walls. Columns come out once their strip of deck is gone.
Water runs on the break the whole time, with a crew member on the hose next to the machine. Concrete and steel are kept apart as they come down, ready for load out.




Where the job is at
As at 10 November 2026, the fencing, protection and saw cutting are done and the crew is working through the demolition of the deck section by section. This page will be updated with the finished result when the ramp is handed back to the joint venture.




Lessons learned on this job
Every job teaches the crew something. These are the ones we are taking from the coach ramp so far.
What worked
- Bringing the right size machine. The 35 tonne excavator reaches the deck from a safe distance and gets through the work far quicker than small plant working under a suspended slab.
- Changing the sequence on site. Strips about 2 metres wide, west to east, kept every piece of deck small enough to control.
- Cutting before breaking. Sawing the deck free from the retained walls meant the anchors and walls were never loaded by the demolition.
What was difficult
- Heavy reinforcing in the deck slowed the saw cutting, so the feed had to be set carefully to stop the blade binding.
- No vehicles in the work area meant every service and tool change was planned around the gate.
- Moving a 35 tonne machine and its attachments interstate takes planning. Transport and timing had to be locked in well before the machine was needed.
If you have something similar
If you need a ramp, deck, platform or structure taken out inside a live site in Queensland, we can bring the cutting, the heavy plant and the crew as one package. Send us the drawings and the constraints and we will give you a method your engineers can check.








Perfect Contracting acknowledges the Aboriginal and Torres Strait Islander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.