Coach Ramp Demolition, Roma Street Station Brisbane

35 tonne excavator and 14 tonne excavator breaking the Roma Street Station coach ramp in Brisbane, water spray on the dust

Project Details

Location

Roma Street Station, Brisbane City QLD

Client

CBGU Design and Construct Joint Venture (Cross River Rail)

Duration

October 2026 to November 2026 (in progress)

In progress, October to November 2026. Perfect Contracting is carrying out the concrete demolition of the old coach ramp at Roma Street Station in Brisbane for the CBGU Design and Construct Joint Venture, as part of the Cross River Rail program. The ramp is a suspended reinforced concrete deck on concrete columns, sitting between retained basement walls that have to stay standing and undamaged when we leave.

This is a big one for our Queensland team. It is the first time Perfect Contracting has run a 35 tonne excavator on a Brisbane job, and we sent it up by road from New South Wales to do it. Paired with a 14 tonne machine and a track mounted wall saw, it has let the crew take the deck down in controlled sections without loading the structure that stays behind.

35 tonne excavator and 14 tonne excavator breaking the Roma Street Station coach ramp in Brisbane, water spray on the dust
Both machines on the ramp: the 35 tonne up top on the deck, the 14 tonne working the low end

The job

The coach ramp is one of the last pieces of the old Roma Street layout. It has to come out so the new station works can carry on around it. The joint venture asked us to remove the deck and its columns, protect the retained walls and their ground anchors, and leave a clean edge for the next trades.

We have worked at Roma Street for the same joint venture since April 2025. The earlier packages, from platform slab demolition to wire sawing and wall penetrations, are on our Roma Street Station project page. The coach ramp is a straight piece of heavy concrete demolition in Brisbane, and a different kind of job to the work inside the station.

Coach ramp deck at Roma Street Station Brisbane before concrete demolition, Brisbane CBD towers behind
The old coach ramp deck before we started, with the CBD right behind it
Concrete coach ramp structure and columns at Roma Street Station Brisbane before demolition
The ramp from below: suspended deck on concrete columns, retained walls either side

What the job involved

  • Anti-throw fencing and screens installed along the ramp edges on night shift before any demolition started
  • Excavators floated in overnight so the street and the busway were clear by morning
  • Timber protection built over the ground anchors on the retained walls
  • Saw cutting along the ramp walls with a track mounted wall saw to free the deck from the structure that stays (concrete cutting in Brisbane)
  • Deck demolition in strips with the 35 tonne and 14 tonne excavators, using hammers, a pulveriser and grabs
  • Column removal once each strip of deck was clear
  • Water suppression on every break for silica dust, with fit tested respirators for the crew
  • Concrete and reinforcing steel kept apart on site for load out

A 35 tonne excavator on a Brisbane job, a first for us

Most of our earlier work at Roma Street was inside the station, done with compact plant and remote controlled demolition machines. The coach ramp needed reach and weight. A suspended deck this size is quicker and safer to take down with a big machine standing well back from the edge than with small gear working underneath it.

So we moved our 35 tonne excavator up from a job in Bathurst. It travelled up over two days with its attachments following on a second truck, and it was floated onto site on night shift with the 14 tonne machine. For a Queensland crew that has built its name on tight, careful work in the city, putting a machine of that size to work in the middle of Brisbane is a real step up. It means we can now bring our own heavy plant to large demolition jobs in Queensland.

35 tonne excavator arriving at Roma Street Station Brisbane on an oversize float at night
The 35 tonne arriving on the oversize float after two days on the road from Bathurst
Oversize float delivering a 35 tonne excavator to Roma Street Station in Brisbane CBD at night
Night delivery outside the station, timed so the street was clear before the morning traffic
Excavator being floated into Roma Street Station Brisbane at night on a low loader
Plant floated in on night shift so the street and the busway were clear by morning
35 tonne and 14 tonne excavators parked side by side at Roma Street Station Brisbane
The two machines on the job. The 35 tonne came up by road from our Bathurst job

What made it hard

The ramp sits inside a working station precinct, with the busway, the station and other contractors all within a short distance of the demolition zone. Nothing could leave the exclusion zone, so the edges were fenced and screened, and the work was held inside barriers every shift.

The walls either side of the ramp are staying. They carry ground anchors that hold the basement in place, so every anchor head was boxed in timber and the deck had to be cut free before it was broken. Vehicles are not allowed inside the work area, so the crew set up to service the plant from the gate and planned each day around that.

The deck itself is heavily reinforced. The saw cutting had to go slowly through the steel, and the crew learned quickly how to set the feed so the blade kept moving without binding.

Timber protection over ground anchors on the retained wall during ramp demolition in Brisbane
Anchor heads on the retained wall boxed in timber before the deck came off
Exclusion zone and restricted access barriers around the coach ramp demolition at Roma Street Station
Exclusion zone held around the work, with the station precinct running on the other side

How it was done

Cut first, break second. That is how we run every job at Roma Street. The cut lines along the ramp walls were marked out and sawn with the wall saw, with cuts about 300 mm deep. Once the deck was separated from the walls that stay, nothing we did to it could pull on the retained structure.

Our site supervisor changed the sequence from the original plan so the deck comes off in strips about 2 metres wide, working from west to east, with the last section left until the end. The 35 tonne excavator works from the ground well back from the edge, breaking and pulling each strip, while the 14 tonne machine clears the rubble and cleans up against the walls. Columns come out once their strip of deck is gone.

Water runs on the break the whole time, with a crew member on the hose next to the machine. Concrete and steel are kept apart as they come down, ready for load out.

Wall saw track fixed along the coach ramp wall at Roma Street Station Brisbane for concrete cutting
Saw track set up on the ramp wall. Every cut line was sawn before any breaking
Concrete demolition Brisbane: 35 tonne excavator breaking the ramp slab with water suppression at Roma Street
Breaking out the deck with the water running on the hammer
35 tonne excavator pulling a section of the concrete ramp slab at Roma Street Station Brisbane
The 35 tonne pulling a cut section back off the retained structure
Ramp deck and columns part demolished at Roma Street Station Brisbane with excavator working
Deck coming down in sections, columns left until their strip was clear

Where the job is at

As at 10 November 2026, the fencing, protection and saw cutting are done and the crew is working through the demolition of the deck section by section. This page will be updated with the finished result when the ramp is handed back to the joint venture.

Excavator clearing concrete rubble and reinforcing steel from the coach ramp at Roma Street Brisbane
Rubble and steel cleared from under the deck as each strip came down
Coach ramp demolition in progress at Roma Street Station Brisbane, deck removed back to the columns
Section by section, working back towards the retained walls
35 tonne excavator demolishing a concrete ramp at Roma Street Station Brisbane with a worker on the water hose for silica dust
Water on the break at all times. One man on the hose while the 35 tonne works the deck
14 tonne excavator on night shift at Roma Street Station Brisbane beside the coach ramp
First night on site: fencing up, machines in, ready for the morning

Lessons learned on this job

Every job teaches the crew something. These are the ones we are taking from the coach ramp so far.

What worked

  • Bringing the right size machine. The 35 tonne excavator reaches the deck from a safe distance and gets through the work far quicker than small plant working under a suspended slab.
  • Changing the sequence on site. Strips about 2 metres wide, west to east, kept every piece of deck small enough to control.
  • Cutting before breaking. Sawing the deck free from the retained walls meant the anchors and walls were never loaded by the demolition.

What was difficult

  • Heavy reinforcing in the deck slowed the saw cutting, so the feed had to be set carefully to stop the blade binding.
  • No vehicles in the work area meant every service and tool change was planned around the gate.
  • Moving a 35 tonne machine and its attachments interstate takes planning. Transport and timing had to be locked in well before the machine was needed.

If you have something similar

If you need a ramp, deck, platform or structure taken out inside a live site in Queensland, we can bring the cutting, the heavy plant and the crew as one package. Send us the drawings and the constraints and we will give you a method your engineers can check.

GET A FREE QUOTE TODAY!

PERFECT CONTRACTING is capable of carrying out project like

Coach Ramp Demolition, Roma Street Station Brisbane

with a quick turn around, give us a call today on (02) 8021 1784. Whether you're undertaking a residential or commercial construction project, we have everything you need to ensure the job is completed on time and to budget.

FREE CALLBACK

TALK TO US

WE CALL BACK WITHIN AN HOUR

Leave your details and a real person will call you - no bots, no queues.

We call back within 1-2 hours. Mon-Fri, during business hours.

Talk to a real personCall now

Aboriginal and Torres Strait Islander flagsPerfect Contracting acknowledges the Aboriginal and Torres Strait Islander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.