Perfect Contracting was engaged by our client Downer Group to supervise detailed demolition works at Munmorah Power Station.
These works required an Unrestricted Demolition Licence to carry out the works. Perfect Contracting supplied our client with one of our most experienced demolition supervisors to assist them in carrying out the works.
These works involved the use of high reach boom lifts, a thirty-tonne mobile crane and experienced riggers and dogmen to dismantle and safely crane down multiple gantry towers within the power station.












Perfect Contracting acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.