Company

SYDNEY Head Office
4/8 Lilian Fowler Place
Marrickville NSW 2204
(02) 8021 1784
1300 737 332

QUEENSLAND Office
23 Aranda Steet
Slacks Creek QLD 4127
(07) 2145 6581

Mon-Fri: 8am-5pm
Sat-Sun: Closed

info@perfectcontracting.com.au

2 Greenwich Rd

GREENWICH-NEW

Project Details

Location

Greenwich, North-Sydney, NSW

Client

Duration

12 months

Perfect Contracting was engaged as the principal contractor at Greenwich in North Sydney, 3km from North Sydney CBD. 

The scope involved the demolition of the existing four-story building & the retention works for the two existing basements and further shoring & underpinning works for the third new basement. 

The job had many technical complexities for the demolition and shoring works, mainly around retaining the existing structures while maintaining access to the shared driveway next door.

The demolition works were engineered top-down methodology utilising demolition robots and small excavators, this also included an external engineered scaffolding system encasing the building to provide protection during the demolition process. The works were completed to the ground level where the next challenge of retaining the shared driveway began. 

Around 75 tonnes of structural steel was required to retain the structure above. Our team of in-house engineers and full-time fabrication team worked together to design, manufacture and install the structural beams and braces.

The steel had to be encased with piles 7 meters under basement level 2 with only 1.8 meters of head clearance. A specialized piling rig with low headroom was used to drill the 3 piles progressively until the required depth was reached.

Due to access constraints, concrete to those piles had to be poured from 20m away using a line pump and had to be finished 0.5 m on top of level 3 which hadn’t been excavated yet. 

Using basic engineering principles and designing the concrete mix specifically for this application, the piles were poured “perfectly” to level prior to basement 3 excavation. This enabled the shared driveway to be retained after the removal of all the supporting columns and slabs below.

Once the shared driveway works were completed, the shoring works had to be carried out with the two existing basement slabs in place, expensive back propping was required to allow for a 50T piling rig to be driven on the existing slab to drive piles 14 meters deep.

The anchoring works took place just after all the pilling was completed, this was achieved by coring drilling and concrete cutting through the existing slabs along the projection of all the anchors to allow the slabs to be retained while being used as a platform for the anchoring works.

This enabled the excavation works to take place that started at the bottom of basement 2 level, which was about 8m under the existing ground level.

The bulk excavation was carried out using our fleet of 35-tonne & 24-tonne Volvo excavators all the way down to basement level 3, moving approximately 12,000 metric tonnes of soil along the way. The final few loads of approximately 1000 tonnes were extracted using a specialised telescopic 70-tonne long-reach excavator with a clamshell attachment.

Projects like these can be challenging at the best of times. Despite many challenges faced by our demolition and civil crews, like the four months of rain including a one-in-one-fifty-year rain event our team members persevered, because that’s what we do, we define generations.

GET A FREE QUOTE TODAY!

PERFECT CONTRACTING is capable of carrying out project like

2 Greenwich Rd

with a quick turn around, give us a call today on (02) 8021 1784. Whether you’re undertaking a residential or commercial construction project, we have everything you need to ensure the job is completed on time and to budget.

Request a Callback!

Let us assist you to find the demolition services you need. Please contact us using the information below or fill out the callback form.

(02) 8021 1784
enquiries@perfectcontracting.com.au

OR

Let us call you back!

We’ll call you back as soon as possible, usually within 10 min.

    aboriginal flagsPerfect Contracting acknowledges the Aboriginal and Torres Strait Isander people as Traditional Custodians of the country on which we live and work. We pay our respects to the Traditional Custodians and Elders past, present and future, and honour their connection to the land and ongoing contribution to society.