Tag: demolition

3 Level Detailed Strip out – TAFE, Ultimo

3 Level Detailed Strip out – TAFE, Ultimo

3 Level Strip out – TAFE Ultimo, Sydney

Perfect Contracting have recently started demolition and stripout works for our client Rork Projects at TAFE Ultimo. These works involve carpet tile removal, gyprock walls, and glass removal. This building is classed as a historical building so it requires a technical demolition and stripout taking extra care to preserve all historical features such as door frames, stairs cases, windowsills, and chandeliers. As the lift in the building was small and is only classed as a personal lift it cannot be used as goods lift. It was assessed by our project manager that the most efficient way of removing all waste material from the building would be to use a scissor lift and skip bin at the side of the building and hand load all material manually into the skip. Our scissor lift operators have their EWP (Elevated Working Platform) tickets and are wearing safety harnesses and full PPE (Personal Protective Equipment) to ensure their safety. For the removal of the glass walls, our team members used our aluminium scaffold and suction pads to manually remove each piece of glass. The carpet tiles are being stripped on each floor and removed via the scissor lift. Special protection was installed on all staircases and balustrades by our client to ensure they remained intact throughout the duration of the project. For this project, we used our brand new 30m3 Skip Bin as this would allow us to load more material out each time. All waste and rubbish material is being loaded out by our new Isuzu Hook truck for recycling. We are also now GreenStar Accredited Waste Removal Specialists we are committed complying with all GreenStar guidelines.

Perfect Contracting specialises in detailed heritage demolition works, with years of expertise working with some of the oldest buildings in Australia.

Tags: , , , , , ,
Continue reading
Detailed Demolition – Balmain, Sydney

Detailed Demolition – Balmain, Sydney

3 Level Detailed Demolition Project - Balmain

Our team members have recently started demolition works for our client Lloyd Group at 73 Beattie St in Balmain. These works involve the detailed three level structural demolition of a heritage building. As this building is historical this requires very technical and precise demolition works to be carried out. Firstly our team members started stripping out offices on the 3rd floor at the back of the building leaving the heritage trusses and roof. Next our team members are beginning works at the front of the building where our client requires the removal of the concrete floor slab and 2nd level to be brought down to ground level. For the removal of the concrete slab it was assessed that the safest and most efficient methodology would be to make a series of deep cuts in the slab both horizontally and vertically with a road saw and then to use our 5ton excavator to remove the slab in pieces. The front facade of the building is also heritage so this must remain intact. Our team members will be back propping the façade with tilt props to ensure it remains intact throughout the entirety of the demolition works. The works being carried out by our team members at the moment are part of stage one of works to be completed for our client. There is three stages in total as this is a very detailed heritage building demolition we take the upmost care in ensuring all heritage structures remain intact. All waste and rubbish material is being loaded out by our Isuzu Hook trucks for recycling. We are now GreenStar Accredited Waste Removal Specialists we are committed complying with all GreenStar guidelines.

Perfect Contracting specialise in detailed heritage demolition works, with years of expertise working with some of the oldest building in Australia.

Tags: , , , , , , ,
Continue reading
Asbestos Removal – Knox Grammar School, Wahroonga

Asbestos Removal – Knox Grammar School, Wahroonga

Perfect Contracting finished asbestos removal works at Knox Grammar School in Wahroonga for our client Maintlink. The works included asbestos removal works, removal of wall and floor tiles and removal of hazardous lead paint from the roof.
Tags: , , , , , , , ,
Continue reading
Half House Demolition – Leichhardt

Half House Demolition – Leichhardt

  Our team members have recently finished half house demolition works for our client Pioneer Projects in Leichhardt, Sydney. The scope of works involved removal of roof sheets, timber frame and insulation. Removal of gyprock walls, removal of bathroom tiles and removal of some external brick walls. Firstly our site supervisor met with our client’s representative on site to discuss the full scope of works and get a better understanding on their requirements. Once they were informed of the work to be carried out our team members began by establishing all tools and equipment on site. After the toolbox talk from our supervisor of the potential hazards on site our team members began with the bathroom tile removal. The bathroom tiles were removed using out Hilti TE800 Jackhammers and Tile Smasher attachments. Once all wall and floor tiles were stripped our team members began loading out the waste and rubble with hand bins into our Isuzu Tipper Truck. Access for this project was limited as there was only a narrow pathway at the side of the house. Next our team members began breaking the concrete slab in the laundry, as per the client request. This was done using our bigger Hilti TE1500 and TE3000 Jackhammers that are designed for breaking up heavy concrete slabs. The final stage of this project was the removal of four external walls at the rear of the house. Firstly our more experienced team members made precise vertical cuts along the wall on both sides of the brick with our Husqvarna K9600 Demolition Saw. This ensures that when the wall was being removed that the adjoining walls are not affected. Once all work was complete on this project all our team members loaded out all waste and rubble into out Isuzu Tipper Truck for recycling.

Perfect Contracting have the knowledge and experience to carry out precise residential demolition works

Tags: , , , , , , ,
Continue reading
Stripout – T2 Domestic Sydney Airport

Stripout – T2 Domestic Sydney Airport

Demolition / Stripout – T2 Domestic Sydney Airport

Perfect Contracting recently finished demolition and stripout works for our client HICON Building at Terminal 2 Sydney Domestic Airport as part of the Sydney Airport’s Retail Expansion of the T2 Terminal. These works involved the demolition and strip out of a number of bathrooms including tile removal, removal of fittings, ceiling tile removal and stud wall removal. For stage one of the works our team members carried out the demolition and strip out of the first bathroom. Our team members firstly setup our zip walls to isolate the area and control the dust created. They then began the removal of the bathroom wall and floor tiles using our Hilti TE 1000 Jackhammers with the Tile Smasher attachment. Once all wall and floor tiles were removed they then removed all bathroom fittings and fixtures. All waste and rubble was loaded into our Tub Bins this allows for a fast removal from the site as our Tub Bins are custom fitted with Fork Lift grips and can easily be loaded into our Skip Bins for a swift removal from site. All throughout the works our team members used our Hilti VC-40 Dry/Wet Vac’s to vacuum up all excess dust ensuring we kept control of the dust. All waste and rubble was removed by our Isuzu Hook and Tipper trucks for recycling as we are committed to reaching our goal of recycling over fifty percent of waste and rubble we remove from sites.

Perfect Contracting have the resources and capacity to carry out large commercial strip out works.

Tags: , , , , , ,
Continue reading
Concrete Penetrations – Chester Hill

Concrete Penetrations – Chester Hill

Perfect Contracting have recently finished concrete penetrations for our client AJW Interiors at Chester Hill. This work involved the concrete penetrations of concrete floor along with matching penetrations on the 1st floor slab to allow for a new lift and lift pit installation. The client requested dust control for this project so firstly our team members setup our Zip Walls around the site to ensure dust was contained. We also used our Hilti VC-40 Dry / Wet Vac’s to extract and clean up dust and rubble as we carried out the work. The floor slab was over 150mm thick so required our team members to use out Husqvarna K6500 High Frequency Ring Saw as this would be only hand demolition saw that could cut down to the depth required. As there was no water supply at the site our team members used our portable Makinex Hose2U waster pumps, these connect directly to the Ring Saw. This water supply keeps the diamonds cool on the blade allowing for a cleaner and more efficient cut. Once all cuts had been made to the slab our team members then used out Hilti TE 1000 Jackhammers to break up all the excess concrete and penetrate through the slab, this would allow our client to install the lift pit shaft. When all the concrete was broken up our team members then loaded out all waste and rubble to our Isuzu Tipper truck to be removed for recycling. They then made one last tidy up using our Hilti VC-40 Dry Vac’s to ensure the area was left as clean as possible before finishing up.

Perfect Contracting can carry out clean and precise Concrete Penetrations in any kind of environment. We can setup Zip Walls and apply dust control measures to ensure the surrounding area’s are not effected

Tags: , , ,
Continue reading
Demolition / Stripout – Novotel, Darling Harbour

Demolition / Stripout – Novotel, Darling Harbour

Demolition and Strip-out of Novotel at Darling Harbour

Perfect Contracting has just started works at Novotel at darling harbour for our clients Reward Hotel Projects. These works include the demolition and stripout of 200+ rooms, taking them back to base ready for a new fit out. This project is working in a live Hotel, which means the hotel is still fully operational. Our team members began works on the first level stripping out all rooms. The scope of works included, bathroom, ceiling, floor and wall strip-out of each room to a back to base. Our team members began works on the site by installing protective hoardings inside the services elevators that would be used for loading out all waste and rubble. Then they installed carpet protection film to ensure the carpet was not damaged when removing waste and rubble. All waste and rubble is loaded into our Tub Bin system this allows us to remove the waste and rubble very fast as it can be wheeled into the service elevator and loaded into our Skip Bins. This system also allows us to separate all waste types as here at Perfect we are committed to recycling 100% of waste and rubbish as one of major core values is to protect the environment. When our team members have finished the back to base strip-out of the first level then they will proceed with the strip-out of each of the upper levels. The Result: The client is very happy with the progress of the works carried out so far and are impressed with how efficient and professional each and everyone of our team members are.

Perfect Contracting have years of experience in providing demolition and strip-out services for the Hospitality Industry, call today to request a site visit! Call us on 1300 737 332!

Tags: , , , , , , , , , , ,
Continue reading
Demolition / Stripout of Ascham School in Edgecliffe

Demolition / Stripout of Ascham School in Edgecliffe

Demolition / Stripout of Ascham School in Edgecliffe in Sydney

Perfect Contracting are currently carrying out demolition and stripout of Ascham School in Edgecliffe for our client Infinity Group PTY Ltd. These works include the demolition of brick walls, strip-out of wall and floor tiles and removal of ceiling slabs and all services.
Tags: , , , , ,
Continue reading
Demolition / Stripout – Sydney International Airport

Demolition / Stripout – Sydney International Airport

Demolition and stripout works carried out at Sydney International Airport for EDT Projects PTY Ltd

Perfect Contracting recently completed a project at Sydney International Airport for EDT Projects PTY Ltd. The works involved the demolition and strip-out of a section of the Sydney International Airport.
Tags: , , ,
Continue reading
Brokk Demolition Robot – 165 Philips St

Brokk Demolition Robot – 165 Philips St

Perfect Contracting are currently using a Brokk Demolition Robot to demolish the stairwell at 165 Philips St. We needed the demolition power of a 15 ton excavator but due to the project being with load and size restrictions, it is impossible to get a excavator of that size into the building. This is where the Brokk 90 comes in; the Brokk 90 is one of the most versatile machines available for demolition in restricted areas. When the job has to be done in a confined space, size really does matter. The goal is to bring as much power and flexibility as possible to the site, and the Brokk 90 achieves it.
Tags: , , , , , , ,
Continue reading

Do you need tools & skilled labour?

Call Perfect Hire 1300 737 332.

Join over 10,000 subscribers and

signup to the Perfect Newsletter today.

CALL NOW